Design, production, delivery and installation of physical protection of the intermediate shafts of 24 OPV5-110 E pumps in BPS workshop

Project: „Design, production, delivery and installation of physical protection of the intermediate shafts of 24 OPV5-110 E pumps in BPS workshop”
Client: „NPP – Kozloduy“
Contract: № 358000001/14.08.2015
Execution: 08.2015÷11.2016

There are 24 pumping units in the BPS-2,3 building. Each unit consists of an electric motor type DVDA-173 / 49-12-16K and a pump OPV5-110E. The connection between them is made by two intermediate shafts and guide bearings. The bearings are housed in housings with guide rings and an oil bath.

The object of this working project is the design, manufacture, delivery and installation of physical protection of the intermediate shafts of all 24 pumps in the BPS shop.

Gallery

Certificate