Project: „Supply of Facility for Treatment and Conditioning of Solid Radioactive Wastes with a High Volume Reduction Factor”
Client: „IBERDROLA“
Contract: №4500032188/18.12.2009
Execution: 12.2009÷2018

 


 

Description: Innovative development of the world’s first installation for significantly reducing the amount of solid radioactive waste by plasma incineration. The scope of the contract includes the design, supply of equipment and construction of the installation on the territory of Kozloduy NPP.

Activities scope:

Design, delivery of equipment and materials and assembly of the whole equipment includes:

  • Part “МТ”- process pipelines
    All auxiliary piping systems for cooling water, compressed air, nitrogen and diesel fuel;
    Thermohydraulic and strength analyzes;
    Water tank for fire extinguishing;
    Gas station and propane-butane tank.
  • Part “МТ”- lifting equipment
    Single-girder crane with lifting capacity 5 t.
  • Part “СК”
    Reconstruction of the building “СК-2”;
    Foundations under the facilities;
    Development of building response spectra, seismic analysis of the building;
    Seismic provision of facilities.
  • Part I & C
    0.4 kV and 6 kV power supplies;
    Lighting installation.
  • Part “АСУТП”
    Management of all auxiliary technological processes;
    Ventilation systems management;
    Interfaces with a SCADA system controlling the Plasma Incineration Facility.
  • Part “ОВиК”
    Management of all auxiliary technological processes;
    Ventilation systems management;
    Interfaces with a SCADA system controlling the Plasma Incineration Facility.
  • Part “ПГС и ПИС”
  • “МОАБ” – partial participation